gantt
title ChargeMind Work Plan
dateFormat YYYY-MM-DD
axisFormat %d/%m/%Y
tickInterval 1week
weekday monday
section Team Setup
Week 1 :a1, 2024-09-30, 7d
section Project Proposal Form
Week 2-3 :a2 after a1, 2024-10-07, 14d
section Project Selection Form
Week 3 :a3, 2024-10-14, 7d
section Project Work Plan
Week 4 :a4, 2024-10-21, 7d
section Literature Review
Week 4-6 :a5, 2024-10-21, 21d
section Marketing Research
Week 4-7 :a6, 2024-10-21, 28d
section Software Requirement Specification
Week 6-10 :a7, 2024-11-04, 35d
section Project Webpage
Week 10-11 :a8, 2024-12-02, 14d
section Software Design Description
Week 11-13 :a9, 2024-12-09, 21d
section Project Report / Tracking Form
Week 14-15 :a10, 2024-12-30, 14d
section Presentation
Week 15-16 :a11, 2025-01-06, 14d