Worklog uptill 28 Feb

Brief:

  • Added suggestions to the survey designed by Kushan and designed the form.
  • Mailed the academic committee for the survey forms and sent out a mass mail
  • MOM all till 29 Feb. (8 MOM's)
  • Revised the SRS version 1 on 18 Feb, Thursday
  • Making charts and survey analysis for SRS
  • Made the project plan sections 1,2,3,5
  • SRS section 2.2, 2.1.1 2.1 created. 1.6 created
  • SRS reviewed final version 1.
  • SRS appendix added.
  • SDLC contributed two sections

Brief: Worklog for 29 Feb and onwards

29 Feb

Work

  • Survey v2 helped design edit and review.
  • Taught Deergha git and helped her set the system up.

Work left

None

1 March

Work

  • Collected survey of 40 people individually.

Work left

To be carried over

  1. Make the TODO app by friday (LEFT)

2 March

Work

  • Read about the TODO app and followed it to make one of my own.

Work left

None

3 March

Work

  • None

Work left

None

4 March

Work

  • Read about Agile development from the Software engineering book.

Work left

None

5 March

Work

  • Read about the different activity diagrams online from tutorials point

Work left

None

6 March

Work

  • Made the Cost estimation document using the COCOCO model

Work left

None

7 March

Work

  • None

Work left

None

8 March

Work

  • System test plan section 1,2,3,4,12,13 Created

Work left

None

9 March

Work

  • System Test plan Sections assigned to Kuljeet Reviewed.

Work left

None

10 March

Work

  • Added a document explaining how agility was incorporated and would be incorporated in the software development process for 3 months.

19 March

Work

  • Re-read the two documents systemtest plan and the SDLC for final verification before entering the testing phase.

25 March

Work

  • Read about travis CI and understood the working of travis

26 March

Work

  • Integrated travis CI for the project in our repository
  • Helped Saloni with a writeup for Travis for the readme document for the git repo.

27 March

Work

  • Made the component icon.js file for the project for all the icons that the project would need.

31 March

Work

  • Made the testing document with few functionality test cases that would be tested.

3 April

Work

  • Worked on the TODO redcuers test cases in Chai Mocha.

5 April

Work

  • Worked on the INTRANET reducers test cases.

7 April

Work

  • Worked on the testing report for unit test cases that are written.

10 April

Work

  • Started working on the termination analysis report

11 April

Work

  • Worked on the termination analysis report

12 April

  • Added more test cases to the document that we functionally tested.

14 April

  • Completed the termination analysis.
  • Added the section of functionality in the outline of testing that we performed.
  • Helped to prepare the presentation slides
  • Got the letter signed from Prof. Pillutla
  • Added sections of the deployment plan