The following timeline is derived from ICU4X 1.0 PRD and is optimized to provide maximal alignment and synergy between progressive feature extension, technical advancements and business evaluations. This is a preamble view. The ICU4X team is focused to deliver quality work in a way that benefits the customers and the team itself in a measurable way. We are using agile project management methodologies and our detailed work is organized in (milestones and sprints).
- 2020
- October
- 0.1 Release (#204)
- November/December
- Post 0.1 clean up and maintenance cycle (Milestone)
- October
- 2021
- January/February
- Locale
- Likely Subtags (#417)
- DateTime
- Day Periods (#435)
- Time zones (#418)
- Components Bag (#481)
- UnicodeSet
- L3a (#478)
- Locale
- March/April
- FFI/WASM exploration (#398)
- 0.2 Release (#239)
- May
- FFI/WASM exploration (#207)
- Data Provider performance (#667)
- Gecko integration experiment
- Test262 evaluation
- June-September
- October-December
- January/February
- 2022
- January-March
- April-June
- 1.0 Release (Milestone)
- Data + API stability
- Full FFI coverage
- Segmenter (#109)
- Time Zone Calculations (#533)
- User-friendly data tooling (multi-blob, source data downloader) (part of #1110)
- Implement locale fallbacking in data loading(#1109)
- Collator (#971)
- Calendrical calculations and formatting for Coptic, Japanese, and Indian National (#534)
- DateTimeFormat modularity / API
- 1.0 Release (Milestone)
- July-December