Strings with a fork don't resolve correctly #64

Open
RHammond2 opened this issue Jan 23, 2023 · 6 comments
Open

Strings with a fork don't resolve correctly #64

RHammond2 opened this issue Jan 23, 2023 · 6 comments
Labels
bug Something isn't working feature request Request a new feature/enhancement

Comments

@RHammond2
Copy link
Contributor

When an array cable string splits into two diverging upstream paths, the upstream cable/turbine connections don't resolve correctly. Likely a customized graph model is required for this scenario instead of a sequentially defined, CSV-based model.

@RHammond2 RHammond2 added bug Something isn't working feature request Request a new feature/enhancement labels Jan 23, 2023
@AJP-47
Copy link

AJP-47 commented Jul 31, 2024

Hi,

My question seems related to this issue, but I could be wrong. I'm looking to model an array loop. In the picture attached, I need to connect the offshore substation with turbine 10 for redundancy. (In case T6 is offline, then T7 to T10 can still send power to the OSS)
image

Is this possible by tweaking the plant layout.csv file?

Thanks

@RHammond2
Copy link
Contributor Author

Hi @AJP-47, unfortunately, neither redundancy, nor forking is enabled in WOMBAT, and there isn't really a great workaround for it other than having separate strings for each prong of the fork.

@AJP-47
Copy link

AJP-47 commented Aug 1, 2024

Hi @RHammond2

Thanks for the response. Can you tell me how I can create a separate fork between T10 and OSS1?

Adding an extra line in the plant layout.csv for T10 does not seem to be the way to go, as WOMBAT assumes its a new turbine and increases the wind farm capacity.

Thanks!

@RHammond2
Copy link
Contributor Author

Unfortunately, there isn't a way to have a turbine on two strings without going into the code and directly modifying the graph layout setup within the wind farm model. The only way to currently model those three turbines is as a separate string from OSS1 -> T10 -> T9 -> T8 -> T7, and not include them on the string OSS1 -> T5 -> ... -> T1.

That said, this is certainly a use case that's worth exploring more, though is of low priority from a project planning perspective at the moment. We're working on finding more funds for the work to push some of these long standing feature ideas up the priority list, but unfortunately there isn't a lot of consideration for this kind of layout at the moment.

@AJP-47
Copy link

AJP-47 commented Aug 1, 2024

Hi Hammond,

I see what you mean. I tried the 2 fork method but I still don't get my redundancy.
image

Thanks a lot for the support! And apologies for crashing this thread, I don't think my redundancy issue is suited here. Would you like me to delete my comments this discussion?

@RHammond2
Copy link
Contributor Author

The model wasn't at all designed around redundancy, so it won't be possible to have the redundancy as-is, though I'm already envisioning how it could be enabled for a case such as this. I would also keep your comments active because it helps provide some evidence for me that people are looking for this functionality, and some of the ancillary considerations.

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
bug Something isn't working feature request Request a new feature/enhancement
Projects
None yet
Development

No branches or pull requests

2 participants