1- Newly assigned:
When a nugget is created by project manager, the nugget will be assigned to resources by project manager. Resources will estimate hours of working on nugget in sequence of workflow. The nugget will stay in this manner until the first resource done his/her task.(Phase status: To do when Hours Worked=0)
2- Need estimate:
Nugget will stay in this condition until the resource who is assigned to this nugget gives an estimate hours of working on this nugget. Resource has got one day to submit an estimate on the nugget, otherwise project manager finds out about this situation.(Phase status: To do when Hours Worked=0)
3- Upcoming nugget:
Nugget will stay in this manner until the start date of the estimate which resource gave to it in previews tab becomes.(Phase status: To do when Hours Worked=0)
4- In-progress nugget:
Nugget will stay in this tab from the start date of the estimate until the end time of the estimate.(Phase status: In progress when Hours Worked >=0 )
The text was updated successfully, but these errors were encountered:
1-
Newly assigned:
When a nugget is created by project manager, the nugget will be assigned to resources by project manager. Resources will estimate hours of working on nugget in sequence of workflow. The nugget will stay in this manner until the first resource done his/her task.(Phase status: To do when Hours Worked=0)
2-
Need estimate:
Nugget will stay in this condition until the resource who is assigned to this nugget gives an estimate hours of working on this nugget. Resource has got one day to submit an estimate on the nugget, otherwise project manager finds out about this situation.(Phase status: To do when Hours Worked=0)
3-
Upcoming nugget:
Nugget will stay in this manner until the start date of the estimate which resource gave to it in previews tab becomes.(Phase status: To do when Hours Worked=0)
4-
In-progress nugget:
Nugget will stay in this tab from the start date of the estimate until the end time of the estimate.(Phase status: In progress when Hours Worked >=0 )